  • Backdrop Term Agreement for MEP Design Services 
  • M05645 - Maytum Hall Boiler Room Stair Repair 
  • 051053 - Feasibility Study: Fenner House 
  • 051038 - Replace Kirkland Plaza
  • 051040 - Maytum Hall Lower Roof Replacement  
  • 051037 - Rehab Lanford Phase II - Exterior  
  • State University Construction Fund (SUCF) PROJECTS 

Project Details:

 

Project -- Backdrop Term Agreement for MEP Design Services 

Consultant: TBD
Contract Limit (Consultant Cost): Not to Exceed $700,000

Expected Start of Services: January 2025
Expected Completion of Services: End of 2027 (3 years, non-renewable) 

LATEST NEWS: Update current through 11/25/2024 --- Consultant Selection Rating Forms have been completed and the campus will be scheduling zoom interviews in the near future. 


Project No. M05645 - Maytum Hall Boiler Room Stair Repair  (Facilities Services MCM Project) 

Consultant: LaBella Associates

Expected Start of Services: Feb./March 2025
Expected Completion of Services: April 2025

LATEST NEWS: Update current through 12/04/2024 --- This project is out for bid. Bids Due 12/17/24. 

Notice to Bidders            Current Plan Holders List


Project No. 051053 - Feasibility Study: Fenner House 

Consultant: LaBella Associates 
Contract Cost: $159,748

Expected Start of Services: Spring 2024
Expected Completion of Services: December 2024

LATEST NEWS: Update current through 11/25/2024 --- LaBella Associates is continuing their work on this project. 


Project: 051038 - Replace Kirkland Plaza

Project Phase: Construction Phase  
Design Cost: $196,548.14
Consultant: Bergmann
Construction Cost: $2,351,821
Contractor: S. St. George Enterprises 

Expected Start of Construction: May 2024
Expected Completion of Construction: November 2024

LATEST NEWS: Update current through 11/25/2024 --- Construction is nearing completion. 

top


Project: 051040 - Maytum Hall Lower Roof Replacement & Maytum Hall Upper Roof Restoration Coating 

Project Phase: Construction Phase  
Design Cost: $155,202
Consultant: Bell & Spina 
Construction Cost: $402,965 / $349,519
Contractor: Jamestown Roofing  / Progressive Roofing 

Expected Start of Construction: May 2024
Expected Completion of Construction: November 2024

LATEST NEWS: Update current through 11/25/2024 --- Upper Roof work is complete; Lower Roof work is nearing completion.

top


Project 051037 - Rehab Lanford Phase II - Exterior 

Project Phase: Contract Award 
Design Cost: $153,872.70
Consultant: Flynn Battaglia Architects 
Construction Cost: TBD
Contractor: TBD

Expected Start of Construction: May 2025
Expected Completion of Construction: August 2025

LATEST NEWS: Update current through 11/25/2024 --- In Contract Award Phase with low bidder, Rodriguez Construction Group.

 

top


Project: 051022-00 Renovate Jewett Hall (SUCF PROJECT

Project Phase: Design Phase   
Consultant: Mitchell Giurgola Architects

LATEST NEWS: Update current through  09/20/2024 -- In pre-bid submission phase with bids due in early December. 

top


Project: 051042 - Replace Turf Field & Track (SUCF PROJECT

Consultant: PHZ Architects, PLLC
Contractor: Lake Shore Paving

LATEST NEWS: Update current through 09/20/2024 --

Artificial Turf Field (Phase I) - Construction Complete.

Track & Field (Phase II) - Bids were received - In review.  

top


Project: 051043 - Replace Emergency Generators (SUCF PROJECT

Project Phase: Construction Phase    
Consultant: Pathfinder Engineers
Contractor: Frey Electric 

LATEST NEWS: Update current through 09/20/2024 -- This project is currently in the construction phase.

top


Project: 051044 - Replace Mechanical Equipment - Rockefeller Arts Center (SUCF PROJECT

Project Phase: Concept / Schematic Design Phase
Consultant: M/E Engineering 

LATEST NEWS: Update current through 09/20/2024 -- This project is currently in the schematic design phase - Consultant submitting reports.  

top


Project: 051045 - Rehab Interior Reed Library - Learning Common (SUCF PROJECT

Project Phase: Schematic Design Phase   
Consultant: Architectural Resources

LATEST NEWS: Update current through 09/20/2024 -- This project is currently in the schematic design phase - Consultant submitting reports.

top


Project: 051047 - Mason Hall Siding (SUCF PROJECT

Project Phase: Construction
Consultant: Holt Architects 
Contractor: Rodriguez

LATEST NEWS: Update current through 09/20/2024 --This project is substantially complete and the punch list is being reviewed. 

top


Project: 051048 - Mason Hall Renovations (SUCF PROJECT

Project Phase: Design Phase
Consultant: Architectural Resources 

LATEST NEWS: Update current through 09/20/2024 -- The concept / schematic documents are in review. 

top